CNATRAINST 1550.6E
14 October 2003
3. To assist the CCC with this effort the following checklist
should be used (Figures C.1 and C.2):
Figure C.1
MONTHS
BEFORE PHASE REQUIRED ACTION
CONFERENCE
The CCC announces the date and location of upcoming
planning and phase conferences and requests SM/CMs
conduct review of their publications. Affected FRS
4
the planning conference.
The CCC collects TCRs from the SM/CMs to present at
the phase conference. Proposed TCRs to be reviewed
3
will be distributed to all affected units.
The planning conference with FRS representatives, the
2
will be held.
CNATRA PTO and CCC determine final agenda items for
phase conference. Agenda items are circulated to all
1
units using curriculum for their review prior to the
conference.
CCMM hosts Curriculum Review Conference while the CCC
and PTO chair the overall conference. Each SM/CM is
0
expected to chair his or her specific portion.
Figure C.2
MONTHS AFTER
PHASE
REQUIRED ACTION
CONFERENCE
PTO provides minutes from conference to CCC who then
tasks SM/CMs with specific conference approved
1
revisions.
2-3
SM/CMs and CCC work revisions.
CCC provides a smooth copy of the instructions and
publications to CNATRA, utilizing Microsoft Word 6.0
4
(or newer). CNATRA approves instructions and
publications and submits CNATRAINST 1542 to CNO for
approval if required.
6
CNATRA publishes new instructions and publications.
Appendix C
C-2